TELUS Kamloops data centre and Kamloops AI Factory
What the public record shows
An operating data centre being expanded into an AI facility, with a cluster-level power figure and two conflicting renewable claims.
TELUS operates a data centre in Kamloops that the Province announced in 2012 as a $75 million project built to LEED Gold standards, with 200 construction jobs and 75 permanent skilled technical positions. TELUS now states it is expanding the facility into a Sovereign AI Factory, leveraging an initial 85 MW of clean, renewable power secured from BC Hydro across a three-site B.C. cluster, with the cluster scaling to over 150 MW and over 60,000 GPUs by 2032.
What is missing
- The 85 MW figure covers the Kamloops expansion and two Vancouver facilities together. The split across sites is not published, so it is recorded as a cluster-level expected peak demand and not as an allocation, a contract or a connection for this facility.
- BC Hydro's 2026 Call for Demand page reports 15 applications totalling close to 800 MW and names no applicants, so no link between this facility and that process can be recorded.
- The water claims are stated as reductions and savings against an unnamed baseline, and cover Kamloops and Rimouski together, so no consumption or withdrawal value is recorded.
- The 2012 jobs figures are commitments. No delivered employment figure has been published.
Open questions
- Two proponent releases state different renewable shares for the same facilities, 99 percent in 2025 and 98 percent in 2026, with no methodology, boundary or matching basis in either. Both are recorded and the value is held as disputed.
Last reviewed . Verification state: proponent-reported. Fairness review: pending. Each identified subject gets a factual correction opportunity before any record containing ownership, control or adverse material is indexed. A correction opportunity is a fairness step, not a veto over sourced public-interest reporting. Corrections go through the contact route.
- Registry ID
- PC-FAC-003
- Aggregation review
- review-required
- Current source
- TELUS and Government of Canada advance work to scale Canada's sovereign AI infrastructurePC-SRC-102
Identity, ownership and control
Who owns and operates the record, with protected commercial detail withheld by reason category instead of silently deleted.
TELUS Communications Inc.
owner-operatorReported- Effective from
- 2025-04-15
- Review status
- verified
British Columbia Hydro and Power Authority
electricity-supplier-stated-by-proponentReported- Effective from
- 2026-05-11
- Review status
- review-required
- Ownership percentProtected
- Control mechanismProtected
Location and authority context
General public location at a security-appropriate precision. Parcel detail is protected, and First Nations process fields are Nation-controlled.
- General location
- Kamloops, British Columbia. The sources name the municipality; no site address or coordinates are recorded here.
- Municipality or regional district
- City of Kamloops
- Land tenure category
- not-disclosed
- Coordinate precision
- municipality
- Watershed
- unknown
- Grid / service territory
- BC Hydro, per the proponent statement that power is secured from BC Hydro. No utility record confirming service to this facility has been retrieved.
- Parcel/site identifierProtected
- First Nations process statusNation-controlled
- Nation-approved public summaryNation-controlled
- Sensitive receptor / emergency contextProtected
The registry does not identify or determine rights holders, consultation or accommodation duties, or consent. Potentially affected Nations are identified only through authoritative processes.
Lifecycle and milestones
Planned versus actual dates stay separate, and a missing date stays visibly unknown.
original-facility-groundbreaking
Reported- Planned date
- No public value
- Actual date
- 2012-06-29
- Source
- Groundbreaking of TELUS Data Centre Means More B.C. JobsPC-SRC-106
ai-factory-in-service
Unknown- Planned date
- No public value
- Actual date
- Not yet recorded
Electricity and grid
Requested, allocated, contracted and connected MW are four different fields. This record shows each one separately with its own state and evidence.
Requested MW
Committed / expectedNot publicly disclosedNot publicly disclosed
- Boundary and method
- No public utility record of a capacity request for this facility has been retrieved. TELUS states an initial 85 MW of clean, renewable power secured from BC Hydro (PC-SRC-102). The release does not say whether that is an allocation decision, a contract or existing service, does not split it across the three named sites, and does not say whether it moved through BC Hydro's 2026 Call for Demand (PC-SRC-105).
- Supply / service class
- unknown
- Additionality
- no claim
Allocated MW
Actual / deliveredNot publicly disclosedNot publicly disclosed
- Boundary and method
- TELUS states an initial 85 MW of clean, renewable power secured from BC Hydro (PC-SRC-102). The release does not say whether that is an allocation decision, a contract or existing service, does not split it across the three named sites, and does not say whether it moved through BC Hydro's 2026 Call for Demand (PC-SRC-105).
- Supply / service class
- unknown
- Additionality
- no claim
Contracted MW
Actual / deliveredNot publicly disclosedNot publicly disclosed
- Boundary and method
- TELUS states an initial 85 MW of clean, renewable power secured from BC Hydro (PC-SRC-102). The release does not say whether that is an allocation decision, a contract or existing service, does not split it across the three named sites, and does not say whether it moved through BC Hydro's 2026 Call for Demand (PC-SRC-105).
- Supply / service class
- unknown
- Additionality
- no claim
Connected MW
Actual / deliveredNot publicly disclosedNot publicly disclosed
- Boundary and method
- The facility operates (PC-SRC-102), so a connected load exists. No public source states it, and it cannot be inferred from the proponent's 85 MW cluster figure.
- Supply / service class
- unknown
- Additionality
- no claim
Peak demand
Committed / expectedReported85 MW
- Boundary and method
- Cluster-level figure, not a figure for this facility. TELUS states an initial 85 MW secured from BC Hydro covering the Kamloops expansion and two Vancouver facilities together (PC-SRC-102). The split across sites is not published, the utility instrument is not named, and the release also states the cluster scaling to over 150 MW by 2032.
- Supply / service class
- unknown
- Additionality
- no claim
Annual energy
Committed / expectedDisputedDisputed
- Boundary and method
- No public annual energy value exists for this facility. This row carries the proponent renewable-share claim attached to the facility, which two proponent releases state differently.
- Supply / service class
- unknown
- Renewable claim
- 98% claimed. Proponent statement that the facilities are powered by 98 percent renewable energy (PC-SRC-102). No boundary, period, matching basis (annual or hourly) or accounting standard is published. An earlier proponent release states 99 percent for the Kamloops and Rimouski AI Factories (PC-SRC-103). Both figures are retained and neither is treated as correct.
- Additionality
- no claim
- Grid upgrade / cost responsibilityProtected
Water, cooling, heat and backup generation
PUE and WUE only appear with their boundary, period, method context and assurance status. Heat that exists is not heat that is reused.
Annual consumption
Committed / expectedNot publicly disclosedNot publicly disclosed
- Measurement boundary
- No boundary published. The proponent claim covers the Rimouski and Kamloops AI Factories together, not Kamloops alone.
- Method and climate/load context
- TELUS states that natural cooling systems reduce water consumption by more than 75 percent compared to traditional data centres, saving 17 million litres of water per year (PC-SRC-103). A stated saving is not a consumption value and the baseline is not named, so no consumption number is recorded.
- Assurance status
- not-reviewed
- Water source / cooling mode
- natural cooling, per the proponent release
- Heat quality and availability
- not-applicable
Annual withdrawal
Committed / expectedUnknownUnknown
- Measurement boundary
- No boundary published.
- Method and climate/load context
- No public withdrawal figure has been retrieved; the proponent releases (PC-SRC-102, PC-SRC-103) state none. Withdrawal and consumption are separate metrics and neither can be derived from the other or from the cooling technology.
- Assurance status
- not-reviewed
- Water source / cooling mode
- not-disclosed
- Heat quality and availability
- not-applicable
Environmental and physical impacts
Baseline, forecast and actual values stay separate, with permits and conditions cited where they exist.
operational-ghg
Committed / expectedNot publicly disclosedNot publicly disclosed
- Boundary, method and period
- TELUS states its AI Factories eliminate over 300 tons of carbon emissions (PC-SRC-103). An avoided-emissions claim against an unnamed baseline is not an emissions inventory. No scope, boundary, period or accounting standard is published, so no value is recorded.
Employment, procurement and community commitments
Committed numbers and delivered numbers are different claims. Each row is labelled as one or the other.
construction-jobs
Committed / expectedReported200
- Unit and definition
- Construction jobs stated in the 2012 Province of British Columbia news release for the original Kamloops data centre (PC-SRC-106). Duration, location and counting method are not published.
permanent-jobs
Committed / expectedReported75
- Unit and definition
- 75 permanent skilled technical positions stated in the 2012 Province of British Columbia news release (PC-SRC-106). This is a 2012 commitment for the original facility.
permanent-jobs
Actual / deliveredUnknownUnknown
- Unit and definition
- No delivered permanent-employment figure has been published for this facility. The 2012 commitment above (PC-SRC-106) is not evidence of delivery.
- Agreement / milestoneProtected
Indigenous ownership, governance and data arrangements
This entire table is Nation-controlled. Nothing from it serializes to the public projection, this page, exports or metadata.
Collection, interpretation, use, retention and publication of this field family are governed by the relevant Nation or authorized body. The registry publishes it only where disclosure is authorized, and no such authorization exists for any current record. Review rules PC-REV-001 and PC-REV-002 in the canonical pack keep this exclusion in force until authorized reviewers clear them.
- Indigenous governance record IDNation-controlled
- Facility IDNation-controlled
- Arrangement typeNation-controlled
- Agreement existence / statusNation-controlled
- Nation-approved public summaryNation-controlled
- Data-governance arrangementNation-controlled
- Disclosure authority referenceNation-controlled
- Disclosure review dateNation-controlled
- Disclosure classNation-controlled
- Value stateNation-controlled
Benefits, procurement, equity or revenue arrangements are never a substitute for rights, title, consultation, accommodation, consent or Nation decision authority.
Compute, sovereignty and access
Compute capacity appears only with its workload, precision and period context. There is no cross-hardware league table, and security detail stays protected.
installed
Not publicly disclosedNot publicly disclosed
- Capacity metric
- No published capacity metric for this facility. TELUS states the three-site B.C. cluster will house over 60,000 GPUs by 2032 (PC-SRC-102), which is a forward-looking cluster count rather than an installed Kamloops capacity, and a device count is not a capability measure.
- Method, period and context
- Proponent releases only. No workload, precision, period, utilisation or measurement method is published, so no comparable capacity value is recorded.
- Access program / audience
- commercial
- Eligibility, price and allocation
- TELUS markets the Sovereign AI Factory to Canadian businesses, entrepreneurs, startups, researchers, public institutions and government organisations. No published eligibility rules, price list, allocation mechanism or public-interest reservation has been retrieved.
- Utilization / delivered outcome
- unknown; no delivered access, utilisation or customer information is published, and customer identities would not be recorded here in any case
- Hardware category / generationProtected
- Residency, control, support, and operationsProtected
- Security attestationProtected
Approvals, reporting and compliance
Instruments, conditions, filings and reported compliance, with the issuing authority named.
- Decommissioning obligation / securityProtected
Commitments versus delivered performance
A commitment is not delivered performance. Targets and actuals sit side by side, and a missing actual stays visibly unreported.
schedule
ReportedTELUS states the Kamloops AI Factory will come online later this year, in a release dated 2026-05-11 (PC-SRC-102).
- Commitment target
- No public value
- Delivered actual
- Not yet reported
- Unit and period
- calendar year 2026; proponent statement with no specific date published
- Due date / status
- 2026; open
Material changes and version history
Corrections and revisions append history instead of overwriting it. Superseded values stay on the record.
Record nature
initial-recordbecame real-public-record on 2026-08-25, recorded 2026-08-25.
- Record
- PC-FAC-003
- Reason and review
- First entry of this record from public sources; staged for steward review and fairness contact, not indexed.
Renewable share
disputed-claim-recorded99 became 98 on 2026-05-11, recorded 2026-08-25.
- Record
- PC-ELEC-014
- Reason and review
- Two proponent releases state different renewable shares for the same facilities. Both are retained, the value is held in a disputed state, and BC + AI has not reconciled them.
Sources and verification
Every value on this page traces to one of these sources, each with its verification status, effective period and review dates.
- TELUS and Government of Canada advance work to scale Canada's sovereign AI infrastructurePC-SRC-102
- Verification
- proponent-reported
- Retrieved
- 2026-08-25
- Last reviewed
- 2026-08-25
- Dispute / correction
- Conflicts with PC-SRC-103 on renewable share (98 percent against 99 percent). Both are retained.
- Groundbreaking of TELUS Data Centre Means More B.C. JobsPC-SRC-106