Public-source recordApproved

150 West Georgia Street data centre site, downtown Vancouver

What the public record shows

An entitled site with a reported power allocation, no disclosed megawatts, and three organisations holding different kinds of control.

Allied Properties REIT's filed Q2 2026 quarterly report states that entitlement and power-allocation for a large-scale AI data centre are in place at 150 West Georgia and that the property is marketed for development and operation by others. Allied is the secured lender under a facility of up to $212 million to Westbank for the land and pre-development costs, held by a first mortgage plus a pledge of shares in a subsidiary partially owned by Westbank. TELUS separately names 150 West Georgia as one of three B.C. facilities in its own cluster announcement and says it will come online in 2029.

What is missing

  • No megawatt figure, utility instrument or counterparty is disclosed for the reported power allocation, so requested, allocated, contracted and connected capacity all remain unrecorded.
  • The underlying City of Vancouver entitlement instrument, its conditions and its expiry were not retrieved.
  • The district-energy heat claim carries no quantity, boundary, period or offtake agreement.

Open questions

  • Who will own and operate the facility is unresolved on the public record: the lender states the property is marketed for development and operation by others, while the proponent release names TELUS as the operator of a cluster including this site.

Last reviewed . Verification state: official-source. Fairness review: pending. Each identified subject gets a factual correction opportunity before any record containing ownership, control or adverse material is indexed. A correction opportunity is a fairness step, not a veto over sourced public-interest reporting. Corrections go through the contact route.

Registry ID
PC-FAC-002
Aggregation review
review-required

Identity, ownership and control

Who owns and operates the record, with protected commercial detail withheld by reason category instead of silently deleted.

  • Westbank Corp.

    borrower-developerReported
    Effective from
    2026-06-30
    Review status
    verified
  • Allied Properties Real Estate Investment Trust

    secured-lenderReported
    Effective from
    2026-06-30
    Review status
    verified
  • TELUS Communications Inc.

    announced-operator-not-confirmedReported
    Effective from
    2026-05-11
    Review status
    review-required
  • TELUS Communications Inc.

    related-project-common-proponentReported
    Effective from
    2026-05-11
    Review status
    review-required
  • Ownership percentProtected
  • Control mechanismProtected

Location and authority context

General public location at a security-appropriate precision. Parcel detail is protected, and First Nations process fields are Nation-controlled.

General location
150 West Georgia Street, downtown Vancouver. Address named in the proponent release and in the lender's filed quarterly report.
Municipality or regional district
City of Vancouver
Land tenure category
not-disclosed
Coordinate precision
civic-address
Watershed
unknown
Grid / service territory
unknown; the filed report states a power allocation is in place but does not name the utility
Authority
City of Vancouver
  • Parcel/site identifierProtected
  • First Nations process statusNation-controlled
  • Nation-approved public summaryNation-controlled
  • Sensitive receptor / emergency contextProtected

The registry does not identify or determine rights holders, consultation or accommodation duties, or consent. Potentially affected Nations are identified only through authoritative processes.

Lifecycle and milestones

Planned versus actual dates stay separate, and a missing date stays visibly unknown.

Electricity and grid

Requested, allocated, contracted and connected MW are four different fields. This record shows each one separately with its own state and evidence.

  • Requested MW

    Committed / expectedNot publicly disclosed

    Not publicly disclosed

    Boundary and method
    Allied's filed Q2 2026 quarterly report (PC-SRC-104) states that entitlement and power-allocation for a large-scale AI data centre are in place at this site. It discloses no megawatt figure, no utility instrument and no counterparty, so no value is recorded.
    Supply / service class
    unknown
    Additionality
    no claim
  • Allocated MW

    Actual / deliveredNot publicly disclosed

    Not publicly disclosed

    Boundary and method
    Allied's filed Q2 2026 quarterly report (PC-SRC-104) states that entitlement and power-allocation for a large-scale AI data centre are in place at this site. It discloses no megawatt figure, no utility instrument and no counterparty, so no value is recorded.
    Supply / service class
    unknown
    Additionality
    no claim
  • Contracted MW

    Actual / deliveredNot publicly disclosed

    Not publicly disclosed

    Boundary and method
    Allied's filed Q2 2026 quarterly report (PC-SRC-104) states that entitlement and power-allocation for a large-scale AI data centre are in place at this site. It discloses no megawatt figure, no utility instrument and no counterparty, so no value is recorded.
    Supply / service class
    unknown
    Additionality
    no claim
  • Connected MW

    Actual / deliveredNot applicable

    Not applicable

    Boundary and method
    The facility is not built (PC-SRC-104), so there is no connected load. A reported allocation is not a connection.
    Supply / service class
    not-applicable
    Additionality
    not-applicable
  • Grid upgrade / cost responsibilityProtected

Water, cooling, heat and backup generation

PUE and WUE only appear with their boundary, period, method context and assurance status. Heat that exists is not heat that is reused.

  • Heat reuse committed

    Committed / expectedNot publicly disclosed

    Not publicly disclosed

    Measurement boundary
    No boundary published.
    Method and climate/load context
    TELUS states the Vancouver facilities are designed to integrate into Creative Energy's downtown district energy system and that recycled waste heat will heat more than 150,000 homes in metro Vancouver (PC-SRC-102). No megawatt-hour quantity, boundary, period, offtake agreement or delivered figure is published. A homes-equivalent comparison is not a delivered energy quantity.
    Assurance status
    not-reviewed
    Water source / cooling mode
    not-disclosed
    Heat quality and availability
    not-disclosed
  • Annual consumption

    Committed / expectedNot publicly disclosed

    Not publicly disclosed

    Measurement boundary
    No boundary published.
    Method and climate/load context
    TELUS states water consumption will be 90 percent lower than traditional data centres, with plans to incorporate recycled water from BC Place (PC-SRC-102). A percentage reduction against an unnamed baseline is not a consumption value, so no number is recorded.
    Assurance status
    not-reviewed
    Water source / cooling mode
    closed-loop liquid cooling, per the proponent release
    Heat quality and availability
    not-applicable

Environmental and physical impacts

Baseline, forecast and actual values stay separate, with permits and conditions cited where they exist.

    Employment, procurement and community commitments

    Committed numbers and delivered numbers are different claims. Each row is labelled as one or the other.

    • economic-contribution

      Committed / expectedNot publicly disclosed

      Not publicly disclosed

      Unit and definition
      TELUS states the cluster will inject $9 billion into the Canadian economy (PC-SRC-102). No method, period, geography or definition is published, and the figure covers the whole cluster rather than this site, so no value is recorded.
    • Agreement / milestoneProtected

    Indigenous ownership, governance and data arrangements

    This entire table is Nation-controlled. Nothing from it serializes to the public projection, this page, exports or metadata.

    Collection, interpretation, use, retention and publication of this field family are governed by the relevant Nation or authorized body. The registry publishes it only where disclosure is authorized, and no such authorization exists for any current record. Review rules PC-REV-001 and PC-REV-002 in the canonical pack keep this exclusion in force until authorized reviewers clear them.

    • Indigenous governance record IDNation-controlled
    • Facility IDNation-controlled
    • Arrangement typeNation-controlled
    • Agreement existence / statusNation-controlled
    • Nation-approved public summaryNation-controlled
    • Data-governance arrangementNation-controlled
    • Disclosure authority referenceNation-controlled
    • Disclosure review dateNation-controlled
    • Disclosure classNation-controlled
    • Value stateNation-controlled

    Benefits, procurement, equity or revenue arrangements are never a substitute for rights, title, consultation, accommodation, consent or Nation decision authority.

    Compute, sovereignty and access

    Compute capacity appears only with its workload, precision and period context. There is no cross-hardware league table, and security detail stays protected.

      • Hardware category / generationProtected
      • Residency, control, support, and operationsProtected
      • Security attestationProtected

      Approvals, reporting and compliance

      Instruments, conditions, filings and reported compliance, with the issuing authority named.

      • Allied's filed Q2 2026 quarterly report states that entitlement and power-allocation for a large-scale AI data centre are in place at 150 West Georgia (PC-SRC-104). BC + AI has not retrieved the underlying City of Vancouver instrument, its conditions or its expiry.

        not-assessed
        Issuing authority
        City of Vancouver
        Review status
        review-required
      • Decommissioning obligation / securityProtected

      Commitments versus delivered performance

      A commitment is not delivered performance. Targets and actuals sit side by side, and a missing actual stays visibly unreported.

      • schedule

        Reported

        TELUS states the 150 West Georgia facility will come online in 2029 (PC-SRC-102).

        Commitment target
        No public value
        Delivered actual
        Not yet reported
        Unit and period
        calendar year 2029; proponent statement, not confirmed by any filed instrument
        Due date / status
        2029; open
      • heat

        Reported

        TELUS states the Vancouver facilities will recycle waste heat into district energy, heating the equivalent of 150,000 homes (PC-SRC-102).

        Commitment target
        No public value
        Delivered actual
        Not yet reported
        Unit and period
        no quantity, boundary or period published; a homes-equivalent figure is a comparison, not a delivered energy quantity
        Due date / status
        no date published; open

      Material changes and version history

      Corrections and revisions append history instead of overwriting it. Superseded values stay on the record.

      • Record nature

        initial-record

        became real-public-record on 2026-08-25, recorded 2026-08-25.

        Record
        PC-FAC-002
        Reason and review
        First entry of this record from public sources; staged for steward review and fairness contact, not indexed.