Public working draftEvidence pack v0.2.0 · Last checked

Evidence and claims ledger

Trace consequential project statements to public sources. See what kind of statement each one is, how its sources are classified, and what the evidence does not establish.

BC + AI publishes this independent public-interest prototype. It is not a regulator, utility, Crown decision-maker, Nation government, official registry, or source of legal or engineering advice.

Claims projected
25
Public sources
29
Evidence classes
6
Repo-only claims excluded
3
The canonical pack does not use a generic “sourced fact” label. It separates law, policy and guidance, external standards, BC + AI recommendations, inference, and unresolved questions. Within every claim, source status shows whether support is official, proponent-reported, independently verified, estimated, disputed, or superseded.
law

law

A currently in-force statute, regulation, or other binding legal instrument in a named jurisdiction. Quote the instrument; do not paraphrase it into a broader duty.

  1. PC-CLM-003launch articlelaw

    The first two-year window is described in the 2026-01-30 news release as 'as much as 400 megawatts' and in regulation/CFD as 100 MW conventional/storage plus 300 MW AI (plus unused storage). That figure is an availability cap, not connected MW.

    Do not collapse this into

    B.C. has connected 400 MW of AI data centres.

    Public sources

    • PC-SRC-013official
      B.C. launching competitive process for clean power in high-demand sectors

      Province of British Columbia · public record

      Published January 30, 2026 · Checked August 19, 2026 · URL resolves

      Official news release. Use for the announced process, 'as much as 400 MW' wording, well-advanced-project carve-out, and September 2026 notification target. Do not upgrade press language into a connected-MW fact.

      https://news.gov.bc.ca/releases/2026ECS0005-000095
    • PC-SRC-002official
      Data Centre Facility and Hydrogen Production Facility Power Supply Regulation

      Province of British Columbia · law/regulation

      Published February 1, 2026 · Checked August 19, 2026 · URL resolves

      B.C. Reg. 8/2026. Binding regulation that caps new capacity BC Hydro may make available and requires competitive processes. Caps are not connected-MW totals.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/8_2026
    • PC-SRC-018official
      2026 Call for Demand: Request for Applications

      BC Hydro · utility process

      Published February 1, 2026 · Checked August 19, 2026 · URL resolves

      Primary utility process document. Selected applicants become eligible to enter or keep a queue position. BC Hydro may reduce the Storage or AI MW allocations. Unsuccessful applicants are ineligible to enter, or are removed from, the interconnection queue. Confidentiality and FOIPPA clauses apply to applications; do not commit application materials.

      https://app.bchydro.com/content/dam/BCHydro/customer-portal/documents/accounts-billing/electrical-connections/2026-cfd-request-for-applications.pdf

    Correction state: No published correction recorded.

  2. PC-CLM-014registrylaw

    Beneficial owner, operator, parent/control entity, related project, and change of control are separate fields. A LOTR or CBCA hit is not a complete control map.

    Do not collapse this into

    The land-title name is the operator and the parent.

    Public sources

    • PC-SRC-008official
      Land Owner Transparency Act

      Province of British Columbia · law/regulation

      Published 2019 · Checked August 19, 2026 · URL resolves

      Creates a public registry of certain beneficial interests in land. It is not a complete beneficial-ownership registry for operating companies, parent entities, or compute contracts. Do not treat a LOTR hit as a full control map.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/19023
    • PC-SRC-025official
      Individuals with significant control: Corporations Canada

      Corporations Canada / ISED · law/regulation

      Published January 22, 2024 · Checked August 19, 2026 · URL resolves

      Federal CBCA filing and partial public disclosure of individuals with significant control, in force 2024-01-22. Applies to federal corporations, not automatically to B.C.-incorporated entities. B.C. corporate transparency remains a separate, version-sensitive question (PC-REV-008).

      https://ised-isde.canada.ca/site/corporations-canada/en/individuals-significant-control
    • PC-SRC-017official
      Land Owner Transparency Registry

      Province of British Columbia / Land Title and Survey Authority of B.C. · policy/guidance

      Published November 30, 2020 · Checked August 19, 2026 · URL resolves

      Official description of LOTR. LTSA operates the registry; the Province enforces LOTA. Public search is not a complete picture of operators, parents, or related compute projects.

      https://www2.gov.bc.ca/gov/content/housing-tenancy/real-estate-bc/land-owner-transparency-registry

    Correction state: No published correction recorded.

  3. PC-CLM-016toolkitlaw

    Local governments do not allocate BC Hydro transmission or generation capacity and do not run the Call for Demand.

    Do not collapse this into

    Council can award the town 50 MW of clean power.

    Public sources

    • PC-SRC-002official
      Data Centre Facility and Hydrogen Production Facility Power Supply Regulation

      Province of British Columbia · law/regulation

      Published February 1, 2026 · Checked August 19, 2026 · URL resolves

      B.C. Reg. 8/2026. Binding regulation that caps new capacity BC Hydro may make available and requires competitive processes. Caps are not connected-MW totals.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/8_2026
    • PC-SRC-006official
      Local Government Act, Part 14: Planning and Land Use Management

      Province of British Columbia · law/regulation

      Published 2015 · Checked August 19, 2026 · URL resolves

      Governs most municipalities and regional districts. City of Vancouver uses the Vancouver Charter, not this Act, for comparable zoning hearings. Public hearings are not always required or even permitted; see s. 464 and later housing-statute amendments.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/r15001_14
    • PC-SRC-004official
      Hydro and Power Authority Act

      Province of British Columbia · law/regulation

      Published 1996 · Checked August 19, 2026 · URL resolves

      Constitutes BC Hydro. Does not give BC + AI, local governments, or this pack any utility power.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/96212_01

    Correction state: No published correction recorded.

  4. PC-CLM-017toolkitlaw

    Public hearings are not always required. Housing-statute amendments prohibit hearings in some zoning cases. City of Vancouver uses the Vancouver Charter.

    Do not collapse this into

    Every data-centre rezoning gets a public hearing.

    Public sources

    • PC-SRC-006official
      Local Government Act, Part 14: Planning and Land Use Management

      Province of British Columbia · law/regulation

      Published 2015 · Checked August 19, 2026 · URL resolves

      Governs most municipalities and regional districts. City of Vancouver uses the Vancouver Charter, not this Act, for comparable zoning hearings. Public hearings are not always required or even permitted; see s. 464 and later housing-statute amendments.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/r15001_14
    • PC-SRC-016official
      Local government public hearings

      Ministry of Housing and Municipal Affairs (B.C.) · policy/guidance

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Provincial guidance summarizing when hearings are required, optional, or prohibited. Guidance, not a substitute for the Local Government Act or Vancouver Charter.

      https://www2.gov.bc.ca/gov/content/governments/local-governments/planning-land-use/local-government-planning/engagement-on-local-planning-land-use/public-hearings
    • PC-SRC-040official
      Vancouver Charter

      Province of British Columbia · law/regulation

      Published 1953 · Checked August 19, 2026 · URL resolves

      City of Vancouver planning and hearing rules live here, not in the Local Government Act. Toolkit copy must branch Vancouver vs other local governments.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/vanch_00

    Correction state: No published correction recorded.

policy/guidance

policy/guidance

Current government, utility, or regulator policy, guidance, engagement material, or process document. It may describe how an authority intends to act; it is not itself a court judgment or a complete legal opinion.

  1. PC-CLM-002launch articlepolicy/guidance

    B.C. clean electricity is valuable and finite. Emerging AI and data-centre requests are large enough that the Province created a paced allocation framework rather than serving every request first-come, first-served.

    Do not collapse this into

    B.C. has unlimited clean power for AI.

    Public sources

    • PC-SRC-012official
      Industrial Electricity Allocation Framework

      Ministry of Energy and Climate Solutions (B.C.) · policy/guidance

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Official provincial policy page describing Bill 31, engagement, the 10 MW threshold, queue-treatment rules, and the 300/100/200 MW two-year call breakdown. Policy/guidance weight, not a substitute for B.C. Reg. 8/2026.

      https://www2.gov.bc.ca/gov/content/industry/electricity-alternative-energy/electricity/industrial-electricity-allocation-framework
    • PC-SRC-013official
      B.C. launching competitive process for clean power in high-demand sectors

      Province of British Columbia · public record

      Published January 30, 2026 · Checked August 19, 2026 · URL resolves

      Official news release. Use for the announced process, 'as much as 400 MW' wording, well-advanced-project carve-out, and September 2026 notification target. Do not upgrade press language into a connected-MW fact.

      https://news.gov.bc.ca/releases/2026ECS0005-000095
    • PC-SRC-001official
      Energy Statutes Amendment Act, 2025 (Bill 31)

      Legislative Assembly of British Columbia · law/regulation

      Published November 19, 2025 · Checked August 19, 2026 · URL resolves

      Primary B.C. statute enabling regulations that restrict or condition electricity service for listed purposes, including storage or processing of electronic data. Royal Assent reported 2025-11-27. Read the in-force Utilities Commission Act text before quoting a duty.

      https://www.bclaws.gov.bc.ca/civix/document/id/bills/billsprevious/1st43rd:gov31-3

    Correction state: No published correction recorded.

  2. PC-CLM-005launch articlepolicy/guidance

    CFD selection makes a project eligible to enter or keep an interconnection-queue position. It is not a supply contract and not an in-service connection.

    Do not collapse this into

    Winners were awarded power.

    Public sources

    • PC-SRC-018official
      2026 Call for Demand: Request for Applications

      BC Hydro · utility process

      Published February 1, 2026 · Checked August 19, 2026 · URL resolves

      Primary utility process document. Selected applicants become eligible to enter or keep a queue position. BC Hydro may reduce the Storage or AI MW allocations. Unsuccessful applicants are ineligible to enter, or are removed from, the interconnection queue. Confidentiality and FOIPPA clauses apply to applications; do not commit application materials.

      https://app.bchydro.com/content/dam/BCHydro/customer-portal/documents/accounts-billing/electrical-connections/2026-cfd-request-for-applications.pdf
    • PC-SRC-012official
      Industrial Electricity Allocation Framework

      Ministry of Energy and Climate Solutions (B.C.) · policy/guidance

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Official provincial policy page describing Bill 31, engagement, the 10 MW threshold, queue-treatment rules, and the 300/100/200 MW two-year call breakdown. Policy/guidance weight, not a substitute for B.C. Reg. 8/2026.

      https://www2.gov.bc.ca/gov/content/industry/electricity-alternative-energy/electricity/industrial-electricity-allocation-framework

    Correction state: No published correction recorded.

  3. PC-CLM-006launch articlepolicy/guidance

    Projects with a signed transmission Facilities Study Agreement or a paid distribution Design Deposit as of the reference date continue under the existing interconnection process and are not proof of CFD participation.

    Do not collapse this into

    Every large B.C. AI site went through the 2026 call.

    Public sources

    • PC-SRC-013official
      B.C. launching competitive process for clean power in high-demand sectors

      Province of British Columbia · public record

      Published January 30, 2026 · Checked August 19, 2026 · URL resolves

      Official news release. Use for the announced process, 'as much as 400 MW' wording, well-advanced-project carve-out, and September 2026 notification target. Do not upgrade press language into a connected-MW fact.

      https://news.gov.bc.ca/releases/2026ECS0005-000095
    • PC-SRC-012official
      Industrial Electricity Allocation Framework

      Ministry of Energy and Climate Solutions (B.C.) · policy/guidance

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Official provincial policy page describing Bill 31, engagement, the 10 MW threshold, queue-treatment rules, and the 300/100/200 MW two-year call breakdown. Policy/guidance weight, not a substitute for B.C. Reg. 8/2026.

      https://www2.gov.bc.ca/gov/content/industry/electricity-alternative-energy/electricity/industrial-electricity-allocation-framework
    • PC-SRC-018official
      2026 Call for Demand: Request for Applications

      BC Hydro · utility process

      Published February 1, 2026 · Checked August 19, 2026 · URL resolves

      Primary utility process document. Selected applicants become eligible to enter or keep a queue position. BC Hydro may reduce the Storage or AI MW allocations. Unsuccessful applicants are ineligible to enter, or are removed from, the interconnection queue. Confidentiality and FOIPPA clauses apply to applications; do not commit application materials.

      https://app.bchydro.com/content/dam/BCHydro/customer-portal/documents/accounts-billing/electrical-connections/2026-cfd-request-for-applications.pdf

    Correction state: No published correction recorded.

  4. PC-CLM-019toolkitpolicy/guidance

    The federal government can fund or brand sovereign-compute projects. That does not allocate BC Hydro capacity or grant B.C. land-use approval.

    Do not collapse this into

    A federal MOU assigned B.C. megawatts.

    Public sources

    • PC-SRC-026official
      Canadian Sovereign AI Compute Strategy

      Innovation, Science and Economic Development Canada · policy/guidance

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Federal program/strategy page. Federal funding or branding does not allocate BC Hydro capacity and does not create B.C. land-use approval.

      https://ised-isde.canada.ca/site/ised/en/canadian-sovereign-ai-compute-strategy
    • PC-SRC-002official
      Data Centre Facility and Hydrogen Production Facility Power Supply Regulation

      Province of British Columbia · law/regulation

      Published February 1, 2026 · Checked August 19, 2026 · URL resolves

      B.C. Reg. 8/2026. Binding regulation that caps new capacity BC Hydro may make available and requires competitive processes. Caps are not connected-MW totals.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/8_2026

    Correction state: No published correction recorded.

standard/comparator

standard/comparator

An external standard, KPI definition, technical paper, or another jurisdiction's model. It may clarify a design choice. It is not B.C. authority unless a B.C. instrument adopts it.

  1. PC-CLM-007launch articlestandard/comparator

    Water withdrawal and water consumption are different measurements. Public claims must label which one they use.

    Do not collapse this into

    The site uses X litres of water without saying withdrawn or consumed.

    Public sources

    • PC-SRC-029official
      ISO/IEC 30134-9:2022 Water usage effectiveness (WUE)

      ISO/IEC JTC 1/SC 39 · standard

      Published 2022 · Checked August 19, 2026 · URL paywalled

      Current international WUE definition. WUE is water consumed per unit of IT equipment energy, not withdrawal, and not a local watershed-stress test. Secondary commentary notes a review may be underway; treat 2022 as current until a new edition is published.

      https://www.iso.org/standard/77692.html
    • PC-SRC-037official
      Water Efficiency in Data Centers

      Lawrence Berkeley National Laboratory Center of Expertise for Energy Efficiency in Data Centers · technical paper

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Technical guidance distinguishing cooling types and water metrics. Standard/comparator. Not a B.C. water licence.

      https://datacenters.lbl.gov/water-efficiency

    Correction state: No published correction recorded.

  2. PC-CLM-008launch articlestandard/comparator

    'Closed loop' does not mean zero water. A recirculating chilled-water loop can still evaporate water at a cooling tower.

    Do not collapse this into

    Closed-loop cooling solves water impact.

    Public sources

    • PC-SRC-037official
      Water Efficiency in Data Centers

      Lawrence Berkeley National Laboratory Center of Expertise for Energy Efficiency in Data Centers · technical paper

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Technical guidance distinguishing cooling types and water metrics. Standard/comparator. Not a B.C. water licence.

      https://datacenters.lbl.gov/water-efficiency
    • PC-SRC-022officialdraft
      Economic and Strategic Assessment Framework for New Data Centres (ERO 026-0853)

      Government of Ontario · comparator

      Published August 13, 2026 · Checked August 19, 2026 · URL resolves

      Draft Ontario consultation, open 2026-08-13 to 2026-09-12. Comparator only. Proposes a three-pillar assessment and explores a separate rate class for new data centres above a demand threshold (example: 1 MW). Not B.C. law.

      https://ero.ontario.ca/notice/026-0853

    Correction state: No published correction recorded.

  3. PC-CLM-009hubstandard/comparator

    PUE without an ISO/IEC 30134-2 measurement category and reporting boundary is not comparable across facilities.

    Do not collapse this into

    This facility is efficient because PUE is 1.2, with no boundary.

    Public sources

    • PC-SRC-028official
      ISO/IEC 30134-2:2026 Power usage effectiveness (PUE)

      ISO/IEC JTC 1/SC 39 · standard

      Published January 2026 · Checked August 19, 2026 · URL paywalled

      Current international PUE definition. Paywalled standard. The Green Grid originated PUE; genuine PUE now means this ISO/IEC definition, including measurement categories and reporting boundaries. A marketing PUE without category and boundary is not this metric.

      https://www.iso.org/standard/30134-2

    Correction state: No published correction recorded.

  4. PC-CLM-010hubstandard/comparator

    WUE is consumed water per IT energy under ISO/IEC 30134-9. It is not withdrawal, not electricity-related water unless the boundary says so, and not a watershed-stress test.

    Do not collapse this into

    Low WUE means the local watershed is fine.

    Public sources

    • PC-SRC-029official
      ISO/IEC 30134-9:2022 Water usage effectiveness (WUE)

      ISO/IEC JTC 1/SC 39 · standard

      Published 2022 · Checked August 19, 2026 · URL paywalled

      Current international WUE definition. WUE is water consumed per unit of IT equipment energy, not withdrawal, and not a local watershed-stress test. Secondary commentary notes a review may be underway; treat 2022 as current until a new edition is published.

      https://www.iso.org/standard/77692.html
    • PC-SRC-037official
      Water Efficiency in Data Centers

      Lawrence Berkeley National Laboratory Center of Expertise for Energy Efficiency in Data Centers · technical paper

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Technical guidance distinguishing cooling types and water metrics. Standard/comparator. Not a B.C. water licence.

      https://datacenters.lbl.gov/water-efficiency

    Correction state: No published correction recorded.

  5. PC-CLM-012registrystandard/comparator

    Heat that exists is not heat that is technically or economically recovered. Heat-reuse claims need temperature, offtaker, hours, and preferably an ERF.

    Do not collapse this into

    The project will heat the neighbourhood, with no offtaker or temperature.

    Public sources

    • PC-SRC-030official
      ISO/IEC 30134-6:2021 Energy Reuse Factor (ERF)

      ISO/IEC JTC 1/SC 39 · standard

      Published 2021 · Checked August 19, 2026 · URL paywalled

      Defines energy reused outside the data centre. Heat that exists is not the same as heat that is technically or economically recovered. ERF is a standard/comparator, not a B.C. permit condition.

      https://www.iso.org/standard/71717.html

    Correction state: No published correction recorded.

  6. PC-CLM-020launch articlestandard/comparator

    Ontario's August 2026 Data Centre Playbook is a draft consultation in another province. It is a comparator, not B.C. law.

    Do not collapse this into

    Canadian provinces now require the Ontario Playbook test.

    Public sources

    • PC-SRC-022officialdraft
      Economic and Strategic Assessment Framework for New Data Centres (ERO 026-0853)

      Government of Ontario · comparator

      Published August 13, 2026 · Checked August 19, 2026 · URL resolves

      Draft Ontario consultation, open 2026-08-13 to 2026-09-12. Comparator only. Proposes a three-pillar assessment and explores a separate rate class for new data centres above a demand threshold (example: 1 MW). Not B.C. law.

      https://ero.ontario.ca/notice/026-0853
    • PC-SRC-023officialdraft
      Ontario Launches Data Centre Playbook

      Government of Ontario · comparator

      Published August 13, 2026 · Checked August 19, 2026 · URL resolves

      Official news release describing the draft Playbook, full-cost electricity language, and 30-day ERO/ORR consultation. Comparator. Economic-growth figures in the release are Ontario government claims, not BC + AI findings.

      https://news.ontario.ca/en/release/1007871/ontario-launches-data-centre-playbook

    Correction state: No published correction recorded.

  7. PC-CLM-021launch articlestandard/comparator

    Global and U.S. data-centre electricity shares (IEA, LBNL) can look modest while a local grid or watershed absorbs a very large impact.

    Do not collapse this into

    Data centres use only 1.5% of electricity, so local concern is misplaced.

    Public sources

    • PC-SRC-035official
      Energy and AI

      International Energy Agency · technical paper

      Published April 10, 2025 · Checked August 19, 2026 · URL resolves

      IEA special report. States data centres used about 1.5% of global electricity in 2024 (415 TWh) and projects roughly 945 TWh by 2030 in the Base Case. Also warns of geographic concentration. Global figures are not B.C. allocation facts.

      https://www.iea.org/reports/energy-and-ai
    • PC-SRC-034official
      2024 United States Data Center Energy Usage Report

      Lawrence Berkeley National Laboratory · technical paper

      Published December 19, 2024 · Checked August 19, 2026 · URL resolves

      U.S. technical paper often cited via DOE. U.S. percentages are not B.C. grid facts. Useful for why national averages hide local concentration.

      https://eta.lbl.gov/publications/2024-lbnl-data-center-energy-usage-report

    Correction state: No published correction recorded.

BC + AI recommendation

BC + AI recommendation

A proposed BC + AI model, disclosure rule, or public-interest test. Not adopted as organizational policy until a named adoption process says so. Not advice to any decision-maker.

  1. PC-CLM-004registryBC + AI recommendation

    Requested, allocated, contracted, and connected MW are four different fields and must not be summed or relabelled as one another.

    Do not collapse this into

    The project is a 50 MW project without saying which MW.

    Public sources

    • PC-SRC-018official
      2026 Call for Demand: Request for Applications

      BC Hydro · utility process

      Published February 1, 2026 · Checked August 19, 2026 · URL resolves

      Primary utility process document. Selected applicants become eligible to enter or keep a queue position. BC Hydro may reduce the Storage or AI MW allocations. Unsuccessful applicants are ineligible to enter, or are removed from, the interconnection queue. Confidentiality and FOIPPA clauses apply to applications; do not commit application materials.

      https://app.bchydro.com/content/dam/BCHydro/customer-portal/documents/accounts-billing/electrical-connections/2026-cfd-request-for-applications.pdf
    • PC-SRC-002official
      Data Centre Facility and Hydrogen Production Facility Power Supply Regulation

      Province of British Columbia · law/regulation

      Published February 1, 2026 · Checked August 19, 2026 · URL resolves

      B.C. Reg. 8/2026. Binding regulation that caps new capacity BC Hydro may make available and requires competitive processes. Caps are not connected-MW totals.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/8_2026

    Correction state: No published correction recorded.

  2. PC-CLM-026registryBC + AI recommendation

    Community-benefit promises, local procurement, public compute access, and delivered outcomes are four fields. Do not report a promise as a delivered outcome.

    Do not collapse this into

    The project will create 400 jobs, listed as a delivered outcome.

    Public sources

    • PC-SRC-013official
      B.C. launching competitive process for clean power in high-demand sectors

      Province of British Columbia · public record

      Published January 30, 2026 · Checked August 19, 2026 · URL resolves

      Official news release. Use for the announced process, 'as much as 400 MW' wording, well-advanced-project carve-out, and September 2026 notification target. Do not upgrade press language into a connected-MW fact.

      https://news.gov.bc.ca/releases/2026ECS0005-000095

    Correction state: No published correction recorded.

inference

inference

A reading that follows from cited sources but is not stated verbatim in any one of them. Must remain attached to those source IDs.

  1. PC-CLM-001launch articleinference

    AI and data-centre facilities are physical industrial infrastructure: land, electricity, cooling, water decisions, transmission, backup generation, and community consent.

    Do not collapse this into

    AI is weightless or 'just software in a warehouse.'

    Public sources

    • PC-SRC-035official
      Energy and AI

      International Energy Agency · technical paper

      Published April 10, 2025 · Checked August 19, 2026 · URL resolves

      IEA special report. States data centres used about 1.5% of global electricity in 2024 (415 TWh) and projects roughly 945 TWh by 2030 in the Base Case. Also warns of geographic concentration. Global figures are not B.C. allocation facts.

      https://www.iea.org/reports/energy-and-ai
    • PC-SRC-013official
      B.C. launching competitive process for clean power in high-demand sectors

      Province of British Columbia · public record

      Published January 30, 2026 · Checked August 19, 2026 · URL resolves

      Official news release. Use for the announced process, 'as much as 400 MW' wording, well-advanced-project carve-out, and September 2026 notification target. Do not upgrade press language into a connected-MW fact.

      https://news.gov.bc.ca/releases/2026ECS0005-000095

    Correction state: No published correction recorded.

  2. PC-CLM-011launch articleinference

    Sitting on a high-renewable utility mix is not the same as additionality. A new large load can still crowd out other electrification or pull on the margin.

    Do not collapse this into

    Because BC Hydro is mostly hydro, the project is additional clean energy.

    Public sources

    • PC-SRC-031official
      ISO/IEC 30134-3:2016 Renewable Energy Factor (REF)

      ISO/IEC JTC 1/SC 39 · standard

      Published 2016 · Checked August 19, 2026 · URL paywalled

      Facility-level renewable-energy share metric. REF is not additionality. A high REF on a hydro-dominated grid does not prove the load caused new clean generation.

      https://www.iso.org/standard/66127.html
    • PC-SRC-012official
      Industrial Electricity Allocation Framework

      Ministry of Energy and Climate Solutions (B.C.) · policy/guidance

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Official provincial policy page describing Bill 31, engagement, the 10 MW threshold, queue-treatment rules, and the 300/100/200 MW two-year call breakdown. Policy/guidance weight, not a substitute for B.C. Reg. 8/2026.

      https://www2.gov.bc.ca/gov/content/industry/electricity-alternative-energy/electricity/industrial-electricity-allocation-framework
    • PC-SRC-035official
      Energy and AI

      International Energy Agency · technical paper

      Published April 10, 2025 · Checked August 19, 2026 · URL resolves

      IEA special report. States data centres used about 1.5% of global electricity in 2024 (415 TWh) and projects roughly 945 TWh by 2030 in the Base Case. Also warns of geographic concentration. Global figures are not B.C. allocation facts.

      https://www.iea.org/reports/energy-and-ai

    Correction state: No published correction recorded.

  3. PC-CLM-013registryinference

    One cross-hardware compute scalar (for example 'H100-equivalent' or 'MW of compute') is unreliable. Compute capacity is hardware-specific.

    Do not collapse this into

    The site is a 2-exascale / 10,000-GPU-equivalent facility without naming chips and dates.

    Public sources

    • PC-SRC-035official
      Energy and AI

      International Energy Agency · technical paper

      Published April 10, 2025 · Checked August 19, 2026 · URL resolves

      IEA special report. States data centres used about 1.5% of global electricity in 2024 (415 TWh) and projects roughly 945 TWh by 2030 in the Base Case. Also warns of geographic concentration. Global figures are not B.C. allocation facts.

      https://www.iea.org/reports/energy-and-ai
    • PC-SRC-034official
      2024 United States Data Center Energy Usage Report

      Lawrence Berkeley National Laboratory · technical paper

      Published December 19, 2024 · Checked August 19, 2026 · URL resolves

      U.S. technical paper often cited via DOE. U.S. percentages are not B.C. grid facts. Useful for why national averages hide local concentration.

      https://eta.lbl.gov/publications/2024-lbnl-data-center-energy-usage-report

    Correction state: No published correction recorded.

  4. PC-CLM-018toolkitinference

    The Province does not, through the CFD, replace local land-use authority or Nation rights.

    Do not collapse this into

    Winning the CFD is a provincial permit to build.

    Public sources

    • PC-SRC-012official
      Industrial Electricity Allocation Framework

      Ministry of Energy and Climate Solutions (B.C.) · policy/guidance

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Official provincial policy page describing Bill 31, engagement, the 10 MW threshold, queue-treatment rules, and the 300/100/200 MW two-year call breakdown. Policy/guidance weight, not a substitute for B.C. Reg. 8/2026.

      https://www2.gov.bc.ca/gov/content/industry/electricity-alternative-energy/electricity/industrial-electricity-allocation-framework
    • PC-SRC-005official
      Declaration on the Rights of Indigenous Peoples Act

      Province of British Columbia · law/regulation

      Published November 28, 2019 · Checked August 19, 2026 · URL resolves

      B.C. statute requiring alignment of provincial laws with UNDRIP and an action plan developed in consultation and cooperation with Indigenous Peoples. It does not authorize this pack, BC + AI, or a municipal toolkit to decide Nation-specific disclosure or consent rules.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/19044
    • PC-SRC-006official
      Local Government Act, Part 14: Planning and Land Use Management

      Province of British Columbia · law/regulation

      Published 2015 · Checked August 19, 2026 · URL resolves

      Governs most municipalities and regional districts. City of Vancouver uses the Vancouver Charter, not this Act, for comparable zoning hearings. Public hearings are not always required or even permitted; see s. 464 and later housing-statute amendments.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/r15001_14

    Correction state: No published correction recorded.

  5. PC-CLM-025hubinference

    Data residency is not data control. Remote administration, subcontracting, and lawful-access paths can sit outside the resident jurisdiction.

    Do not collapse this into

    Servers in B.C. means the data is sovereign.

    Public sources

    • PC-SRC-039official
      Personal Information Protection and Electronic Documents Act

      Parliament of Canada · law/regulation

      Published 2000 · Checked August 19, 2026 · URL resolves

      Federal private-sector privacy statute. Data residency is not automatically required by PIPEDA. Do not equate 'sovereign capability' with a PIPEDA citation.

      https://laws-lois.justice.gc.ca/eng/acts/P-8.6/
    • PC-SRC-026official
      Canadian Sovereign AI Compute Strategy

      Innovation, Science and Economic Development Canada · policy/guidance

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Federal program/strategy page. Federal funding or branding does not allocate BC Hydro capacity and does not create B.C. land-use approval.

      https://ised-isde.canada.ca/site/ised/en/canadian-sovereign-ai-compute-strategy
    • PC-SRC-046official
      Canadian Centre for Cyber Security guidance landing page

      Canadian Centre for Cyber Security · policy/guidance

      Published date unavailable · Checked August 19, 2026 · URL resolves

      Federal cyber guidance portal. Individual ITSG/ITSP documents must be cited by number when a registry field claims a specific control baseline. This pack does not select a baseline.

      https://www.cyber.gc.ca/en/guidance

    Correction state: No published correction recorded.

unresolved question

unresolved question

A material gap, conflict, or rights question that this pack records and does not answer. Includes Nation-specific, legal, utility, engineering, privacy/security, and accessibility review items.

  1. PC-CLM-023toolkitunresolved question

    Nation-controlled information is not a subset of ordinary commercial confidentiality and is not a municipal FOI residual category.

    Do not collapse this into

    We redacted Nation materials under the same heading as trade secrets.

    Public sources

    • PC-SRC-027official
      The First Nations Principles of OCAP®

      First Nations Information Governance Centre · standard

      Published 1998 · Checked August 19, 2026 · URL unavailable

      OCAP® is a registered trademark of FNIGC. It is a First Nations information-governance standard, not a subset of commercial confidentiality and not a municipal FOI exception. Required citation: OCAP® is a registered trademark of the First Nations Information Governance Centre (FNIGC); see www.FNIGC.ca. This pack does not apply OCAP® to a named Nation or invent Nation-specific rules.

      https://fnigc.ca/ocap-training/
    • PC-SRC-005official
      Declaration on the Rights of Indigenous Peoples Act

      Province of British Columbia · law/regulation

      Published November 28, 2019 · Checked August 19, 2026 · URL resolves

      B.C. statute requiring alignment of provincial laws with UNDRIP and an action plan developed in consultation and cooperation with Indigenous Peoples. It does not authorize this pack, BC + AI, or a municipal toolkit to decide Nation-specific disclosure or consent rules.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/19044
    • PC-SRC-009official
      Freedom of Information and Protection of Privacy Act

      Province of British Columbia · law/regulation

      Published 1996 · Checked August 19, 2026 · URL resolves

      Governs public-body records and personal-information holdings. It is not a licence to publish Nation-controlled information, and it is not a substitute for OCAP®.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/96165_00

    Correction state: No published correction recorded.

  2. PC-CLM-024toolkitunresolved question

    This pack does not decide Nation-specific disclosure or consent rules. Those require Nation-led work (#1995) and remain unresolved here.

    Do not collapse this into

    Best practice is for Nations to disclose X.

    Public sources

    • PC-SRC-005official
      Declaration on the Rights of Indigenous Peoples Act

      Province of British Columbia · law/regulation

      Published November 28, 2019 · Checked August 19, 2026 · URL resolves

      B.C. statute requiring alignment of provincial laws with UNDRIP and an action plan developed in consultation and cooperation with Indigenous Peoples. It does not authorize this pack, BC + AI, or a municipal toolkit to decide Nation-specific disclosure or consent rules.

      https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/19044
    • PC-SRC-015official
      Declaration Act Action Plan

      Province of British Columbia · policy/guidance

      Published March 30, 2022 · Checked August 19, 2026 · URL resolves

      Five-year action plan required by s. 4 of the Declaration Act. Policy/guidance implementing a statute. It does not authorize BC + AI to speak for Nations or to design a First Nations pathway (see #1995, PC-REV-001).

      https://declaration.gov.bc.ca/declaration-act-action-plan/
    • PC-SRC-027official
      The First Nations Principles of OCAP®

      First Nations Information Governance Centre · standard

      Published 1998 · Checked August 19, 2026 · URL unavailable

      OCAP® is a registered trademark of FNIGC. It is a First Nations information-governance standard, not a subset of commercial confidentiality and not a municipal FOI exception. Required citation: OCAP® is a registered trademark of the First Nations Information Governance Centre (FNIGC); see www.FNIGC.ca. This pack does not apply OCAP® to a named Nation or invent Nation-specific rules.

      https://fnigc.ca/ocap-training/

    Correction state: No published correction recorded.

  3. PC-CLM-027launch articleunresolved question

    Named-facility electricity shares (for example a public claim that one proponent holds 38% of the two-year allocation) are disputed until queue status, CFD participation, and which MW term is meant are independently verified.

    Do not collapse this into

    Repeat the 38% figure as an official allocation fact.

    Public sources

    • PC-SRC-042disputed
      Sovereign AI for Whom?

      BC + AI / Kris Krüg · public record

      Published May 12, 2026 · Checked August 19, 2026 · URL resolves

      Already-published BC + AI News letter. Usable for already-public organizational voice. Facility-specific claims inside it remain proponent-reported or disputed until independently verified. Membership counts in that letter are dated May 2026 and are superseded by later approved stats.

      https://bc-ai.ca/news/sovereign-ai-for-whom
    • PC-SRC-013official
      B.C. launching competitive process for clean power in high-demand sectors

      Province of British Columbia · public record

      Published January 30, 2026 · Checked August 19, 2026 · URL resolves

      Official news release. Use for the announced process, 'as much as 400 MW' wording, well-advanced-project carve-out, and September 2026 notification target. Do not upgrade press language into a connected-MW fact.

      https://news.gov.bc.ca/releases/2026ECS0005-000095
    • PC-SRC-018official
      2026 Call for Demand: Request for Applications

      BC Hydro · utility process

      Published February 1, 2026 · Checked August 19, 2026 · URL resolves

      Primary utility process document. Selected applicants become eligible to enter or keep a queue position. BC Hydro may reduce the Storage or AI MW allocations. Unsuccessful applicants are ineligible to enter, or are removed from, the interconnection queue. Confidentiality and FOIPPA clauses apply to applications; do not commit application materials.

      https://app.bchydro.com/content/dam/BCHydro/customer-portal/documents/accounts-billing/electrical-connections/2026-cfd-request-for-applications.pdf

    Correction state: No published correction recorded.

Challenge or correct the record

Name the claim or source ID, explain what appears wrong, and point to public evidence we can check. Material corrections append to project history rather than silently replacing the prior record.

Request a correction